Nov 8, 2026

Park Restoration Project Update, November 2026

If you've visited the park this autumn, you'll have noticed plenty of activity across the site as contractors continue to deliver the first phase of our exciting restoration project. Significant progress has already been made, with improvements taking shape in several key areas.

Play Area

Contractors have recently returned to complete the works to improve play facilities in the park.

  • The mound has been turfed.

  • New play surfacing has been laid in high footfall areas.

  • Railings altered to prevent dogs from entering the park.

  • Reseeding and turfing within the play area.

  • Additional rubber mat installed along zip line.

Expected completion: November 2026

Park Railings and Gates

Work to restore the park's historic railings and gates is well underway.

  • The railings have been carefully removed and are currently being sandblasted and repainted.

  • Existing coping stones have been lifted and are being rebedded.

  • New Bath stone coping stones have been commissioned to replace the missing sections adjacent to the gate pillars.

  • The park gates are scheduled for removal and restoration in November.

Expected completion: December 2026

The Amphitheatre

The transformation of the amphitheatre is now clearly visible.

  • Original paving blocks have been lifted, cleaned and set aside for reuse within the new design.

  • Foundations have been excavated and poured, providing the base for the new tiered seating.

  • Blockwork construction is underway, revealing the shape of the remodelled amphitheatre.

  • The finished walls will be faced with attractive Purbeck stone, creating a high-quality natural finish.

Expected completion: February 2027

New Toilet Block

Construction of the new toilet facilities continues to make good progress.

  • Foundations have been completed.

  • Drainage infrastructure has been installed and waterproofing measures put in place.

  • Internal and external blockwork is now being constructed in preparation for the next stages of the build.

Expected completion: February 2027

Drinking Fountain, Bottle Refill Station and Dog Water Bowl

Work has begun on a new hydration point for park visitors and their four-legged companions.

  • Foundations have been installed adjacent to the new toilet block.

  • Water supply and drainage pipework has been completed.

Expected completion: February 2027

Wilderness Area

Enhancements to the wilderness area are helping to improve access and create new opportunities for learning and exploration.

  • New safety gates have been installed.

  • A stone-surfaced path is being constructed to provide improved access to the pond and dipping platform.

  • Posts for the new canvas shelter have been installed.

  • The site's willow trees will be pollarded or coppiced as part of their traditional long-term management, helping to maintain the health and character of this important wetland habitat.

Expected completion: November 2027

Composting Bays

The new composting facility is taking shape and will provide both environmental and operational benefits.

  • The concrete base has been completed.

  • Steel and timber structures have been installed to create three composting bays.

  • Interpretation signage has been designed and will be installed to promote the benefits of composting.

Once operational, green waste from the park will no longer need to be transported to Yate for processing. This will reduce vehicle movements, fuel consumption and carbon emissions, while also enabling us to produce nutrient-rich compost on site for use in the community garden and wider park.

Expected completion: November 2027

Community Garden

Improvements continue to support gardening activities and sustainable water management.

  • Two 1,000-litre rainwater harvesting tanks have been installed to collect water from the Grounds Maintenance Hut. These will soon be clad to improve their appearance.

  • Posts have been erected to support a temporary shelter, which will be installed next summer.

Boundary Improvements

Our programme of traditional hedgelaying will continue in December, with sections of the park's eastern and southern boundaries being restored and managed using this historic countryside conservation technique. Hedgelaying helps to strengthen mature hedgerows, improve wildlife habitats and maintain the park's landscape character.

Thank you for your patience and support while these improvements are carried out. We look forward to sharing further updates as the restoration project progresses.

Significant progress has been made on the first phase of our restoration project, with improvements taking shape across the park.

In partnership with

Help Us!

Be Part of Something Special

From planting days to community events, your involvement makes Kingswood Park thrive. Join our friendly group of volunteers and help shape the future of this cherished space.

In partnership with

Help Us!

Be Part of
Something Special

From planting days to community events, your involvement makes Kingswood Park thrive. Join our friendly group of volunteers and help shape the future of this cherished space.

In partnership with

Illustration of green grass with yellow wheat-like stalks and simple leaf shapes in the background.

Help Us!

Be Part of
Something Special

From planting days to community events, your involvement makes Kingswood Park thrive. Join our friendly group of volunteers and help shape the future of this cherished space.

Contact the
Friends of Kingswood Park Group

© 2026 Friends of Kingswood Park

Made and maintained with ❤ by digiDen.studio